Paraná River Project - Schedule: Fieldwork

You are Here: ScheduleFieldwork

Standing in the Paraná Paraná Paraguay mixing Getting ready for more GPR

Fieldwork

There will be three low flow, one high and one high/medium flow field seasons. The exact timing of fieldwork is subject to logistical constraints and selection of appropriate flows, but they are provisionally scheduled for LOW: April 2008, October 2008, August 2009, HIGH: February 2010, MEDIUM: April/May 2010. GPR work will be undertaken in each low flow season and MBES and aDcp work conducted in medium and high flow field seasons. Resistivity surveys will be undertaken in two low flow seasons. There will be a need to ensure that high quality field data are supplied at the right times for validating the numerical modelling work.